The most important piece in setting up MRP in VISUAL falls under the PLANNING tab in Part Maintenance.

The first thing you need to be aware of is that you can have a unique set of planning parameters for each of your Independently Planned Warehouses AND one set of planning parameters for your other warehouses deemed Universal

What the difference between Universal and Independently planned warehouses? Read this

MRP Fundamentals - How to set up part planning in part maintenance

 

Warehouse ID
Select the Warehouse ID or Universal you are wanting to set the planning parameters for. Please note that VISUAL will always default to Universal when you first call up a part.

Planner User ID
This is a free form field that can be used for searching and reporting. Basically, you can enter values that you can easily filter on.

Buyer User ID
As with the Planner User ID, this is a free form field that can be used for filtering - however values entered in this field will be maintained in the VISUAL database and existing values can be selected from a dropdown box.

Safety Stock Qty
This is used where you would like to maintain a certain quantity level for a part. You may want to consider this for parts with long lead times. MRP will look at upcoming demand and supply and your projected qty always wants to meet this safety stock quantity.

Leadtime (in Days)
This is the number of days it takes between the time you place a supply order and when the part is received into inventory. Leadtime is always in days. This value is used to compute when to release an order and set the want date of supply orders.

Min/Max/Multiples Of
These fields are here to help you make better decisions and plan more efficiently.

Min - the minimum quantity that MRP will generate a planned order

Max - the maximum amount that the MRP will generate a planned order

NOTE – for clarification, this only caps the quantity of an individual planned order. So, if you have demand for a 1000 units for a part and you have a Max value of 200. MRP will generate 5 planned orders for 200 each. This allows you to better manage your orders.  For instance, you may shop floor constraints where you can only manufacture 200 units at a time – so you would not want your work orders with build quantities greater than 200.

Multiples of – allows you to define the multiple to use when MRP plans an order. For example, if Part A is ordered in multiples of 10, and you have demand for 7, then MRP will generate a planned order for 10.

 

Order Policy
This is the key indicator that will determine how MRP will plan for the part.

Not Planned
MRP will not generate planned orders. It will completely ignore this part. FYI – This is the default setting when creating a part.

Discrete
Most commonly used when first starting with MRP. This setting will have MRP replenish exactly the quantity by which demand exceeds supply. It will plan the supply order to match each element of demand. 

So if you have 3 orders creating demand, one for 2, one for 5 and one for 10 ... MRP will create 3 planned supply orders - with quantities of 2, 5, and 10 respectively

It’s a one to one relationship unless you use min/max/multiple of – then planned orders will reflect those parameters.

Period Supply
MRP will generate planned order to meet a shortfall on a given date – PLUS the number of days you specify in the Days of Supply field

Fixed and EOQ
These settings a basically the same. Regardless of the amount of the shortage – MRP will plan for orders using the fixed amount specified in the Order Qty field

Master Scheduled
Planned orders are generated to meet quantities and dates specified in the Master Production Scheduled. This option is only available if you are using Advanced MRP and dealing with forecasts

 

 

Days of Supply
Used with period of supply

Order Qty
Used with Fixed and EOQ

Order Point Qty
If the part is NOT PLANNED, you can use this field to enter the minimum quantity you want to keep on hand. When it falls below that amount it will appear on the Order Point Report (in the Material Planning Window) for you to place an order. NOTE – MRP WILL NOT plan the order – you need to manually create it when needed

Order Up to Qty
If the part is NOT PLANNED – you can use this field in conjunction with the Order Point Qty field to determine quantity to use to create a supply order.

 

Next: The Inherit Demand Warehouse Option

 

Comments

Feed You can follow this conversation by subscribing to the comment feed for this post.

The comments to this entry are closed.

WHO IS VISUALNUGGETS?

Rich Ferlatte
Results Driven VISUAL Specialist

CONSULTING SERVICES

Of course, I am available for hire!

ERP Implementations & Upgrades
Analytics & Reporting
Integrations & Macros
General VISUAL Support

ONLINE VISUAL WORKSHOPS

Taking it to the next level and designing a program around "Hands On VISUAL Training".

Check them out - there's sure to be one to interest you!

Operational Workshops
Reporting Workshops
Financial Workshops
Inventory Workshops
Quality Workshops

VISUAL EXTENSIONS

BOM Xploder
Drastically improve your BOM visibility and discover shortages at ANY level of your bill of material no matter how deep.
SmartViews
See, analyze, and track information that helps you better support individual, departmental, and your company’s performance metrics and goals.
eBoard - Financial Power App
Developed for accounting professionals looking for powerful and easy-to-use GL reporting software. Access live financial data, drill down to support details and export financial statements to Excel in one click.
Inventory App
This Inventory Reconciliation App provides a systematic approach to control and manage your Visual inventory effectively and efficiently
Credit Card Integration
Easily accept and process credit card payments right from within VISUAL.
ACH Document Processing
Leveraging VISUAL's payment scheduling and batch payment functions, with the added convenience, performance, and security of Electronic Funds Transfer payment processing.
Latitude Manifest & Shipping System
A seamless multi-carrier shipping solution that integrates to Infor VISUAL ERP. See how it can simplify your small parcel and LTL shipping and package tracking.
Sales Tax Automation with AvaTax
Easily automate sales and use tax in VISUAL with AvaTax. No more manually entering data or uploading rate tables and tax information.
Workforce Management with Kebrite Solutions
Streamlines the collection of Job, Labor, Payroll, Time & Attendance, and a vast array of HR related data-- with live VISUAL integration.